Refrigerant piping diagram
Single circuit only for 38AJ/AZ 008-036 units
Soldered plug with
pressure equalisation
port. To be removed
during installation.
General recommendations for field installation
Thermostatic expansion valve (TXV) and solenoid valve
The thermal expansion valve sensing bulb must be
installed after at least two 90° bends at the evaporator
outlet.
Ideally the TXV should be installed in a vertical pipe run.
If that is not possible, the valve may be rotated through a
full 90°, with the horizontal pipe remaining at the base.
The TXV and solenoid valves are installed as shown in
Figs. 1 to 5 (pages 9 and 10).
- Liquid line solenoid valves are not necessary, if
single-circuit evaporators are used and the evaporator
has sufficient capacity to hold the whole refrigerant
charge. In this case the unit wiring must be modified;
please refer to Carrier Service Bulletin No. SB 005-
76-96 E.
- Solenoid valves are needed with dual-circuit
evaporators to deactivate the upper section of the
evaporator coil and reduce the load on the
compressor (capacity unloaders operated by suction
pressure).
Legend:
1 Condenser
2 Liquid line valve
3 Filter drier
4 Sight glass
5 Fan cycling pressure switch
6 Suction valve
NOTE: The typical refrigeration circuit diagram shown does
not apply to all control types used.
7 Compressor
8 Discharge valve
9 Muffler
A Circuit 1
B Circuit 2
C Option No. 97
Installation of piping
IMPORTANT:
In order to prevent vibration and possible pipe breaks
install proper pipe supports for all pipes at the point
where they leave the unit.
On all units, relieve the pressure of the holding charge
before opening the circuit.
Open all service valves:
- on models 014 to 074, open the compressor suction
and discharge valves
- on all models, open the liquid line shut-off valves.
Remove the protective cap from the Schrader port in the
liquid line valve and press on the valve depressor to
release the holding charge (nitrogen).
Unsolder the plugs and prepare the pipes for connection.
Install the filter-drier and moisture indicator (for 38AZ
units these must be specific for R-407C), as shown in
Figs. 1 to 5. Select the filter-drier for maximum unit
capacity and minimum pressure drop. Install the filter-
drier in the liquid line before the expansion valve and the
moisture indicator just after the shut-off valve in the same
line. These are available as factory-fitted option 97.