Single--Piece Installation
The following steps should be followed for the installation of the single-- piece
configuration.
1. Remove cover from Equipment Control Module by pressing the two tabs
on the bottom edge and pulling away. Route wires through large hole in
Equipmen t Control Module. Level Equipment Control Module against
wall (for aesthetic value only -- Equipment Control Module need not be
leveled for proper operation) and mark wall through 2 mounting holes.
2. Drill two 3/16 --in. mounting holes in wall where marked. Thermidistat
Control may be mounted to a standard junction box if desired. Hole pat-
tern on Equipment Control Module matches junction box mounting
holes.
3. Secure rear plastic Equipment Control Module to wall with 2 screws and
anchors provided. Additional mounting holes are available for more se-
cure mounting if needed. Make sure all wires extend through hole in
Equipment Control Module.
4. Adjust length and routing of each wire to reach proper connector block
and terminal on Equipment Control Module with 1/4--in. extra length.
See Fig. 14.