Installation
8 RTU Open
Using the rooftop equipment control power transformer
1 Remove power from the 24 Vac transformer.
2 Remove connector assembly from RTU Open's
connector.
3 If the rooftop equipment has thermostat connection terminals, connect wiring harness
wire 1 to R,
and
wire 3 to C. Alternately, connect the control power transformer wires to
connector wires 1 (24
Vac) and 3 (Gnd).
4 Apply power to the rooftop equipment.
5 Measure the voltage at the RTU Open’s
terminals 1 and 3 to verify that the voltage is within the
operating range of 21.6–26.4 Vac.
6 Attach harness to RTU Open connector
.
The harness and connector are keyed and must be oriented properly for correct installation.
7 Verify that the
LED is on and the
LED is blinking.
Using an auxiliary control power transformer
If you use a separate control power transformer, it is essential that the auxiliary transformer and the rooftop
transformer are in-phase. You
verify this prior to connecting the auxiliary transformer to the RTU Open.
Follow these steps:
1 Verify the available primary voltage at the rooftop equipment.
2 Remove power from the rooftop equipment and install the appropriate auxiliary transformer. Follow the
manufacturer’s installation instructions.
3 Ground one leg of the auxiliary transformer’s secondary wiring.
4 Apply power to the rooftop equipment. Measure the potential between the rooftop equipment control
power and auxiliary transformer's secondary hot (non-grounded) legs. If the voltage measured is less
than 5 volts, the transformers are in-phase; proceed to step 7. If you measure a voltage greater than 24
Vac, then the phases are reversed.
5 Correct the phase reversal by either of the following methods:
○ Remove the ground from the secondary at the auxiliary transformer and connect it to the other
secondary
○ Reverse the primary wiring at the auxiliary transformer
6 Repeat step 4 to rewire.
7 Remove connector assembly from RTU Open's
connector.
8 Connect the auxiliary transformer wires to
wires
(24 Vac) and
(Gnd).
9 Apply power to the transformer.
10 Measure the voltage at the RTU Open’s
-
and
to verify that the voltage is within the operating
range of 21.6–26.4 Vac.
11 Attach harness to RTU Open's connector
. See illustration below.
The harness connectors are keyed and must be oriented properly for correct installation.
12 Verify that the
LED is on and the
LED is blinking.