Carrier 42C,V Manual de instalación Pagina 46

  • Descarga
  • Añadir a mis manuales
  • Imprimir
  • Pagina
    / 88
  • Tabla de contenidos
  • MARCADORES
  • Valorado. / 5. Basado en revisión del cliente
Vista de pagina 45
46
8. Anchor risers as required:
a. Do not fasten risers rigidly within each unit.
Risers must be free to move within pipe chase
in response to normal vertical expansion and
contraction. The unit internal piping is designed to
accommodate a total riser vertical movement of
±
3
/
4
in., due to thermal expansion and/or contrac-
tion, when positioned properly at the jobsite.
b. Built-in risers must be anchored at some point
to building structure. Unit design accommodates
up to 1
1
/
2
-in. expansion and contraction in riser
assemblies when positioned properly at the job-
site. Risers must be anchored to the building struc-
ture to limit expansion and contraction movement
to a maximum of 1
1
/
2
inches. Riser anchoring and
expansion compensation is not included in the fac-
tory-supplied unit and must be field provided.
While some special riser features are available
from the factory, riser end caps, air vents, and/or
flushing loops are normally provided on the job by
the installer.
9. Test the system for leaks after the connections are com-
pleted. When testing with air or some other gas, it might
be necessary to tighten stem packing nuts on some valves
to maintain air pressure in the riser. Pressure testing risers
with water should be done with the unit service valves
closed to prevent flushing debris into the unit valve pack-
ages. This will also allow risers to be drained down after
testing in the winter to avoid freeze-up problems. In the
event that leaking or defective components are discov-
ered, the sales representative must be notified before any
repairs are attempted. All leaks should be repaired before
proceeding with the installation.
10. After system integrity has been established, pull the riser
insulation back into place over the joint and glue or seal
to prevent sweating and heat loss or gain. Internal chilled
water piping and valves are located over the drain pan
and need not be insulated.
11. If required, fireproof where necessary. Any fireproofing
requirements where risers or piping penetrate floors or
walls are the responsibility of the installer. This work
should be done only after all pressure testing is complet-
ed. The fireproofing method used must accommodate
pipe expansion and contraction and the piping must be
protected from abrasion and chemical attack. The pipe in-
sulation also must be maintained to prevent sweating and
must be protected from wear or erosion at the joint be-
tween the insulation and the fireproofing material.
42 SU Units
— The unique design of the universal stack fan
coil unit allows for field configuration for each unit. Air dis-
charge, riser, drain, and outside air knockouts have been strate-
gically located on each unit. Risers, shown with unit, are for
reference only. All risers are factory fabricated and shipped
loose for field installation.
It is important that you identify all of the unit feature loca-
tions and which knockouts you intend to use before proceeding
with the installation. See Fig. 43-47. Also, it must be deter-
mined whether your application requires a Mating Unit (prima-
ry/secondary) and its configuration. Consult your local sales
representative or the factory for further details on primary/sec-
ondary arrangements.
Potential 42SU Unit Configurations
Risers: Three Locations — The pre-installed supply, return,
and drain risers (2-pipe or 4-pipe applications) can be oriented
on any of three sides of the unit (see Fig. 43).
NOTE: Risers cannot be installed on the return air side of the
cabinet.
Unit orientation is determined based on the location of the
risers in the building. The riser side of the universal stack unit
always determines the rear of the unit. See Fig. 44.
Return Air: Single Location — The return air/access panel
may then be oriented on the left, right, or front of the unit.
Supply Air: Five Locations (4 sides and top) includes stitched
design for
1
/
2
-in. duct flanges.
Outside Air: Two Locations — Either side adjacent to the
return air opening.
NOTE: Outside air opening may be used on a side if risers are
configured on that same side.
Supply, Return, and Drain Riser Installation
1. Three sides of each universal stack unit have four supply
and return riser knockouts along the center and one drain
knockout near the lower part of the unit (see Fig. 45).
Identify whether your application uses a 2-pipe or 4-pipe
configuration.
a. Two-pipe configurations typically use the two
inner riser knockouts.
b. Four-pipe configurations will use all four riser
knockouts.
IMPORTANT: Chilled water and hot water risers should
never be piped to drain down into the condensate riser.
Extensive water damage can occur due to drain over-
flow. Drain chilled and hot water risers to a remote loca-
tion away from the unit such as sink, room or floor
drains.
42SU
CABINET
RETURN AIR
HR CRDHS
CS
HR CRDHS CS
HR CRDHS
CS
D
CR
HS
CS
HR
R
D
S
HR = HOT WATER RETURN
HS = HOT WATER SUPPLY
D = DRAIN
CR = COLD WATER RETURN
CS = COLD WATER SUPPLY
R = RETURN
D = DRAIN
S = SUPPLY
2- or 4-PIPE
Fig. 43 — 42SU Unit Configuration
a42-4283
REAR
RISER SIDE
42SU
CABINET
RIGHT
FRONT
LEFT
Fig. 44 — 42SU Unit Orientation
a42-4284
Vista de pagina 45
1 2 ... 41 42 43 44 45 46 47 48 49 50 51 ... 87 88

Comentarios a estos manuales

Sin comentarios