Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53420010-01 Printed in U.S.A. Form 42-5SI CL-1 1-14 Replaces: 42-4SI
START-UP CHECKLIST FOR 42C,D,S,V SERIES FAN COIL AIR CONDITIONERS
I. Project Information
Job Name _______________________________________________________________________
Address ________________________________________________________________________
City ______________________________________________State __________ Zip __________
Installing Contractor _______________________________________________________________
Sales Office _____________________________________________________________________
Start-up Performed By _____________________________________________________________
INSPECTION, INSTALLATION, AND START-UP CHECKLIST
ITEM COMPLETE ITEM COMPLETE
Receiving & Inspection Electrical Connections
1. Unit received undamaged 35. Refer to unit wiring diagram
2. Unit received complete as ordered 36. Connection incoming power service(s)
3. “Furnish only” parts accounted for 37. Install and connect “furnish only” parts
4. Unit arrangement/hand correct 38. All field wiring in code compliance
5. Unit structural support complete and correct Unit Start-Up
Handling & Installation 39. General visual unit and system inspection
6. Mounting grommets/isolators used 40. Check for proper fan rotation
7. Unit mounted level and square 41. Record electrical supply voltage
8. Proper access provided for unit and accessories 42. Record ambient temperatures
9. Proper electrical service provided 43. Check all wiring for secure connections
10. Proper overcurrent protection provided 44. Close all unit isolation valves
11. Proper service switch/disconnect provided 45. Flush water systems
12. Proper chilled water line size to unit 46. Fill systems with water/refrigerant
13. Proper hot water line size to unit 47. Vent water systems as required
14. Proper refrigerant line sizes to unit 48. All ductwork and grilles in place
15. Proper steam line sizes to unit 49. All unit panels and filters in place
16. Proper steam condensate trap on return line 50. Start fans, pumps, chillers, etc.
17. Proper steam supply pressure to unit (10 psi max) 51. Check for overload condition of all units
18. All service to unit in code compliance 52. Check all ductwork and units for air leaks
19. All shipping screws and braces removed 53. Balance air systems as required
20. Unit protected from dirt and foreign matter 54. Record all final settings for future use
Cooling/Heating Connections 55. Check piping and ductwork for vibration
21. Protect valve package components from heat 56. Check all dampers for proper operation
22. Mount valve packages 57. Verify proper cooling operation
23. Connect field piping to unit 58. Verify proper heating operation
24. Pressure test all piping for leaks 59. Reinstall all covers and access panels
25. Install drain line and traps as required 60. Verify proper condensate drainage
26. Insulate all piping as required
27. Install drip lip under piping as required
28. Connect risers from 42SGM to 42SGS models
29. Connect risers to unit coil valve package (if risers
are shipped/installed separately)
Ductwork Connections
30. Install ductwork, fittings, and grilles as required
31. Flexible duct connections at unit
32. Proper supply and return grille type and size used
33. Control outside air for freeze protection
34. Insulate all ductwork as required